Close Menu
AGC NewsAGC News
  • Home
  • News
    • Advocacy
    • Economics
    • Energy & Environment
    • Infrastructure
    • Building
    • Procurement
    • Labor & HR
    • Safety & Health
    • Technology
    • Workforce Development
  • AGC Videos
  • Constructor Magazine
    • Digital Publications
    • Online Exclusives
    • Sponsored Content
  • ConstructorCast
  • News Releases
Latest News

AGC Safety & Health Town Hall – June 4

May 19, 2025

Watch the Highlights from AGC’s 2025 Annual Convention in Columbus!

May 16, 2025

AGC Fights to Preserve Industry Access to Courts

May 15, 2025
Facebook X (Twitter) Instagram
Facebook X (Twitter) Instagram
AGC NewsAGC News
  • Home
  • News
    • Advocacy
    • Economics
    • Energy & Environment
    • Infrastructure
    • Building
    • Procurement
    • Labor & HR
    • Safety & Health
    • Technology
    • Workforce Development
  • AGC Videos
  • Constructor Magazine
    • Digital Publications
    • Online Exclusives
    • Sponsored Content
  • ConstructorCast
  • News Releases
AGC NEWSLETTERS
AGC NewsAGC News
Home » ConsensusDocs’ Two New Documents Help Facilitate Success for GMP Contracts and Directed Changes
Construction Law

ConsensusDocs’ Two New Documents Help Facilitate Success for GMP Contracts and Directed Changes

February 21, 2023Updated:March 6, 2024No Comments3 Mins Read
Facebook Twitter LinkedIn Email
Office with sledgehammer in front, lawyers and clients discussing court issues or justice at meeting Law and order. The concept of courts and legislatures
Share
Facebook Twitter LinkedIn Email

In light of price escalation, supply chain challenges, and inflation, more industry practitioners are considering and using cost-of-the-work agreements that may or may not include a guaranteed maximum price (GMP).  ConsensusDocs publishes several cost-of-the-work agreements and recently released a new standard contract document to support a cost-of-the-work agreement with a GMP as well as a directed change order standard form.

Setting the GMP

When a GMP is used, it is set by amendment. The ConsensusDocs 230 Standard Agreement Between an Owner and Constructor with General Conditions (Cost of the Work with a Fee and a GMP) assumes a GMP. For the ConsensusDocs 230, to set the GMP amount and completion dates, contracting parties may use ConsensusDocs’ just published ConsensusDocs 230.1 amendment to the ConsensusDocs 230. Before this publication, users would have to make their own amendment or modify other ConsensusDocs documents.

Parties should consider this new document when they possess sufficient certainty for a project to set the GMP as well as the date of substantial completion and the date of final completion. Sometimes, when there is more price uncertainty, parties wait longer in the project completion to set the GMP.  When the contract amount is set early, one consideration is for the parties to include more incentives to compensate for the extra risk. Shared savings are often used in these situations. The ConsensusDocs Guidebook includes a couple of different options for language that parties might insert for shared savings, such as a price escalation clause, allowances and contingency amounts; refer to the section about Amendment 1 to the ConsensusDocs 500. 

Directed Changes

Another just-published contract document is the revised ConsensusDocs 203. This contract document can be used as a unilateral order issued by the Owner to the Constructor to perform a change to the work that has not been agreed upon. If agreed upon, then the ConsensusDocs 202 change order form should be used. Notably, the ConsensusDocs 203 contract document can now also be used when an Owner provides field instructions or other information that does not necessarily impact price or time. This document was revised because the permissible uses of an interim directive have expanded to include field instructions under general conditions and term in ConsensusDocs. For example, when a Constructor stops work for unexpectedly encountering hazardous conditions, an Owner can then instruct the Constructor through an interim directive to resume its services once the condition has been safely remediated or controlled. And such instructions may or may not change the contract price or contract time. These revisions make the expanded efficacy of interim directives clearer. (The American Institute of America (AIA) contract documents use the terminology of construction change directives for what ConsensusDocs terms as an interim directive.)   

Additional Resources

AGC Article: When is the Price Right? Setting the GMP for Design-Build

ConsensusDocs Guidebook

Questions about the content of these new documents may be directed to Brian Perlberg, ConsensusDocs’ Executive Director & Senior Counsel at bperlberg@consensusdocs.org.

Building Federal/Heavy Highway Infrastructure Utility
Share. Facebook Twitter LinkedIn Email

Related News

AGC Safety & Health Town Hall – June 4

May 19, 2025

Watch the Highlights from AGC’s 2025 Annual Convention in Columbus!

May 16, 2025

AGC Fights to Preserve Industry Access to Courts

May 15, 2025

House Pieces Together Reconciliation Package

May 15, 2025
Add A Comment

Comments are closed.

Latest News

AGC Safety & Health Town Hall – June 4

May 19, 2025

Watch the Highlights from AGC’s 2025 Annual Convention in Columbus!

May 16, 2025

AGC Fights to Preserve Industry Access to Courts

May 15, 2025

Your source for AGC news. Find us on social media to learn more about the Associated General Contractors of America.

Connect with us:

Facebook X (Twitter) Instagram YouTube LinkedIn
© 2025 Associated General Contractors of America.
  • Home
  • AGC.org
  • Get In Touch
  • Convention
  • Notice of Permission to Use
  • Privacy Policy
  • Antitrust Policy

Type above and press Enter to search. Press Esc to cancel.