Close Menu
AGC NewsAGC News
  • Home
  • News
    • Advocacy
    • Economics
    • Energy & Environment
    • Infrastructure
    • Building
    • Procurement
    • Labor & HR
    • Safety & Health
    • Technology
    • Workforce Development
  • AGC Videos
  • Constructor Magazine
    • Digital Publications
    • Online Exclusives
    • Sponsored Content
  • ConstructorCast
  • News Releases
Latest News

AGC Weighs in on DBE Changes

November 5, 2025

Federal Court Blocks DOT’s Attempt to Condition Transportation Funds on Immigration Cooperation

November 5, 2025

The Game of Risk

November 5, 2025
Search
Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors
Facebook X (Twitter) Instagram
Facebook X (Twitter) Instagram
AGC NewsAGC News
  • Home
  • News
    • Advocacy
    • Economics
    • Energy & Environment
    • Infrastructure
    • Building
    • Procurement
    • Labor & HR
    • Safety & Health
    • Technology
    • Workforce Development
  • AGC Videos
  • Constructor Magazine
    • Digital Publications
    • Online Exclusives
    • Sponsored Content
  • ConstructorCast
  • News Releases
AGC NEWSLETTERS
AGC NewsAGC News
Home » New Federal Construction General Permit for Stormwater Discharges in Effect
Energy & Environment

New Federal Construction General Permit for Stormwater Discharges in Effect

March 10, 2022Updated:December 6, 2023No Comments3 Mins Read
Facebook Twitter LinkedIn Email
Pollution of the environment by waste from pipes or drainage. The concept of nature pollution sewerage. Discharge of toxic or contaminated water into a river or lake.
Share
Facebook Twitter LinkedIn Email

On Feb. 17, the newly revised 2022 construction general permit (CGP) for stormwater discharges from construction activities took effect.  The CGP applies to operators of construction sites in a few areas where the U.S. Environmental Protection Agency (EPA) is the NPDES (National Pollutant Discharge Elimination System) permitting authority.  More importantly, NPDES authorized states that oversee their own stormwater permitting programs use it as a model for their permits.  AGC supports the use of general permits as an effective tool to streamline the permit process and reduce administrative burdens for those projects with minimal impact.  (Individual permits are available for larger-scale impacts.)   AGC engaged in significant outreach with the agency to discuss ways to improve the permit.  And although the permit has new requirements that can add cost for permittees, such as turbidity “benchmark” monitoring for dewatering discharges to sensitive waters, the agency sought to provide clarity on several points where AGC members have demonstrated to them confusion with the previous permit.

The new CGP addresses several points where AGC requested greater clarity to help permittees better understand the requirements. For example, EPA clarified the difference between routine maintenance (minor repairs and upkeep) and corrective actions (significant repair and/or replacement).  The agency has also provided greater specificity on when inspections are required following rain events.  The agency also made the following changes that AGC supported.  (See this AGC news article to read AGC’s comment letter.)

  • Added flexibility for pollution control of some types of construction waste/ materials.
  • Clarification in the permit that permittees may keep stormwater documentation in electronic form. 
  • Clarification of seasonally dry periods in arid/semi-arid areas

The CGP has new requirements for additional perimeter controls, additional chemical controls, photo documentation, detailed dewatering requirements including turbidity benchmark monitoring for dewatering discharges to sensitive waters, making observations offsite for sedimentation, and inspection training.  You can read a clean and red-lined version of the permit (that clearly shows the changes) from EPA’s resources webpage for the 2022 CGP.  EPA has also prepared a guide, called Monitoring and Inspection Guide for Construction Dewatering, to provide guidance on the new requirements (available online – scroll down to the section on “How Do I Conduct Turbidity Benchmark Monitoring at My Site?”).

Lastly, EPA requested feedback on several provisions that it has, at this time, chose not to change. It did not clarify the definition of operator (i.e., determines who is required to obtain the permit).  The agency also did not extend the waiting period for the permit from 14 to 30 days as they had considered in the proposal—a provision which AGC did not support.  They also did not change the site stabilization from the existing five-acre disturbance threshold; although this issue appears unresolved and may be revisited in future versions.

For more information, contact Melinda Tomaino at melinda.tomaino@agc.org.

Building Federal/Heavy Highway Infrastructure Utility
Share. Facebook Twitter LinkedIn Email

Related News

AGC Weighs in on DBE Changes

November 5, 2025

Federal Court Blocks DOT’s Attempt to Condition Transportation Funds on Immigration Cooperation

November 5, 2025

AGC to OSHA: Don’t Fix What Isn’t Broken 

November 4, 2025

AGC Safety & Health Town Hall – December 3

November 4, 2025
Add A Comment
Leave A Reply Cancel Reply

Latest News

AGC Weighs in on DBE Changes

November 5, 2025

Federal Court Blocks DOT’s Attempt to Condition Transportation Funds on Immigration Cooperation

November 5, 2025

The Game of Risk

November 5, 2025

Your source for AGC news. Find us on social media to learn more about the Associated General Contractors of America.

Connect with us:

Facebook X (Twitter) Instagram YouTube LinkedIn
Search
Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors
© 2025 Associated General Contractors of America.
  • Home
  • AGC.org
  • Get In Touch
  • Convention
  • Notice of Permission to Use
  • Privacy Policy
  • Antitrust Policy

Type above and press Enter to search. Press Esc to cancel.